Miami-Dade Water and Sewer (WASD) Project

#MSV The Miami-Dade Water and Sewer Department (WASD) has embarked on a Capital Improvement Program to provide necessary upgrades to the water and sewer infrastructure to continue providing high quality services, protecting public health, and the environment. One of these projects is an emergency installation of a new 8-inch water line that runs along NE 99 Street from NE 8 Avenue to NE 10 Avenue, and on NE 8 Avenue and NE 9 Avenue from NE 98 Street to NE 99 Street in the Village of Miami Shores The new water main will enhance water quality and pressure in the community by replacing aging infrastructure. In addition, properties that have the water meter located in the rear will have their service relocated to the front. The connections on private property will be funded by the Department and coordinated closely with each individual homeowner. Please refer to the map on the reverse side for more details of the project.
 
Project Presentation Slides provided by the Miami-Dade Water and Sewer Department (WASD) : Installation of an 8-inch Water Main.pdf
 
Project Information | Schedule:
The installation of the new water line will begin on August 23, 2021 and is scheduled to be completed by November 2021. The construction work will occur from 8:00 a.m. to 5:00 p.m. Monday through Friday, and some Saturdays as needed. Workers will take steps to minimize impacts, but you may experience some noise and intermittent traffic disruptions. In advance, we thank you for your support as the department works on this necessary infrastructure improvement.
 
Project at a Glance:
• Construction will begin on August 23, 2021 and is scheduled to be completed by November 2021.
• Once the project is completed, final restoration of the road will follow.
• The areas surrounding the project will be restored at the conclusion of the project.
• The project will not affect the water or wastewater services in your area.
 
Fact sheet - Emergency Installation of 8-inch Water Main_Page_1.png (1.71 MB)Fact sheet - Emergency Installation of 8-inch Water Main_Page_2.png (1015 KB)